Issue - meetings

Planned Maintenance 2018-19

Meeting: 17/04/2018 - Strategy and Resources Committee (Item 55)

55 Planned Maintenance 2018-19 pdf icon PDF 99 KB

The report notes progress and changes to the current planned maintenance programme and seeks approval for 2018/19 programme of proposed works

Additional documents:

Decision:

The Committee:

(1)          Noted the current position/progress on the planned maintenance programme;

(2)          Noted the changes made to the programme under authority delegated to Officers;

(3)          Authorised the carry forward of unspent budget in 2017/18 to 2018/19

(4)          Authorised Officers to proceed with the 2018/19 proposed planned maintenance works;

(5)          Authorised virement from the property reserve to fund shortfall for 2018/19.

Minutes:

A report was presented to the Committee that noted progress and changes to the current planned maintenance programme and sought approval for the 2018/19 programme of proposed works.

The report highlighted that the Property Maintenance Reserve stood at £402,000 as at 1 April 2017.  During 207/18, a sum of £129,000 had been released from the reserve principally to fund completion of the outstanding items from the 2016/17 programme. An underspend of £27,000 was forecast for 2017/18, giving a projected reserve balance of £300,000 as at 31 March 2018.

There was provision of £210,000 for planned maintenance within the approved 2018/19 revenue budget. The proposed schemes for 2018/19 collectively exceeded the approved 2018/19 budget by £70,000. If approved, the funding of this shortfall from the Property Maintenance Reserve would reduce the projected reserve balance to £230,000.

The Committee:

(1)          Noted the current position/progress on the planned maintenance programme;

(2)          Noted the changes made to the programme under authority delegated to Officers;

(3)          Authorised the carry forward of unspent budget in 2017/18 to 2018/19

(4)          Authorised Officers to proceed with the 2018/19 proposed planned maintenance works;

(5)          Authorised virement from the property reserve to fund the shortfall for 2018/19.