Meeting: 07/11/2019 - Planning Committee (Item 44)

44 The Royal Automobile Country Club (RAC), Old Barn Road, Epsom, Surrey, KT18 7EW pdf icon PDF 145 KB

Variation of Condition 2 (drawings) of Planning ref: 18/00645/FUL, dated 14.11.2018, to amend the engineering design of the Reservoir

Minutes:

Description

Variation of Condition 2 (drawings) of planning ref: 18/00645/FUL dated 14 November 2018, to amend the engineering design of the Reservoir.

Recommendation

Following the granting of planning permission in November 2018, work had commenced on site, however during the course of survey works and engineering checks it was established that engineering adjustments to the form of the reservoir were required.

The application sought technical design changes to the reservoir only which would not impact the capacity of the reservoir (6 million gallons), maintenance area, access to the site or the power line constraints.

Officers had assessed the application against planning policy and it was not considered to adversely impact the Green Belt or the ecological and biodiversity potential of the site.

Decision

Planning permission is PERMITTED as per the original conditions detailed below with the only change being to the approved drawings as set out in Condition No.2.

Conditions:

(1)            The development hereby permitted shall be begun before the expiration of three years from the date of 14 November 2018.

Reason: To comply with Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 (1) of the Planning and Compulsory Purchase Act 2004. The development hereby

(2)            The development hereby permitted shall be carried out in strict accordance with the approved drawings:

RAC_SLP_09_05.18 – Site Location Plan – dated 31.05.18

MWE_RAC_PPS_25_08.19 – Planning Phase Sections – dated 15.08.19

MWE_RAC_PPP_24_08.19 – Planning Phase Plan – dated 15.08.19

Reason: For the avoidance of doubt and to ensure that the development is carried out in accordance with the approved plans to comply with Policy CS5 of the Core Strategy (2007). 

(3)            The development shall be carried out in accordance with the details of the pump house, approved under application ref: 19/00086/COND, granted 15 May 2019

Reason: To secure a satisfactory appearance in the interests of the visual amenities and character of the locality in accordance with Policy CS5 of the Core Strategy (2007) and Policies DM9 and DM10 of the Development Management Policies 2015.

(4)            The development shall be carried out and retained in accordance with the details of the fence(s), approved under ref: 19/00086/COND, granted 15 May 2019

Reason: To secure a satisfactory appearance in the interests of the visual amenities and character of the locality in accordance with Policy CS5 of the Core Strategy (2007) and Policies DM9 and DM10 of the Development Management Policies 2015.

(5)            The reservoir land forming and development, shall be carried out in strict accordance with the agreed recommendations for Tree Work and Tree Protection as detailed in the Arboricultural Assessment produced by SJA dated July 2018 reference SJA air 18095-01C

Reason: To protect the trees on site which are to be retained in the interests of the visual amenities of the locality in accordance with Policy CS5 of the Core Strategy (2007) and Policies DM5 and DM9 of the Development Management Policies 2015.

(6)            The development shall be carried out in accordance with the agreed details of the  ...  view the full minutes text for item 44