Decision details

Epsom and Ewell Community Infrastructure Levy - Annual Funding Awards 2026

Decision Maker: Strategy and Resources Committee

Decision status: For Determination

Is Key decision?: No

Is subject to call in?: No

Decision:

Following consideration, the committee resolved with 6 votes for and 1 abstention to:

(1)        Approve and ratify the funding recommendations of the CIL Working Group for each of the bids set out in paragraph 4 of the report, subject to the deletion of the wording “to replace unsafe stepping stones” from the summary provided for Strategic Project 3 – New Footbridge across the Hogsmill River.

Report author: Ian Mawer

Publication date: 15/07/2026

Date of decision: 14/07/2026

Decided at meeting: 14/07/2026 - Strategy and Resources Committee