ICT Datacentre and Infrastructure

Decision Maker: Strategy and Resources Committee

Decision status: For Determination

Is Key decision?: Yes

Is subject to call in?: No

Purpose:

To agree the operation of the ICT datacentre and infrastructure.

Decision:

The Committee agreed:

(1)          Option 3C for the Joint Data Centre with Elmbridge Borough Council hosted at a third party datacentre;

(2)          The funding from existing capital budgets of £63,000 and the use of £139,600 additional capital funds as detailed in Table 3 contained in Annexe 1 to the report (considered exempt from publication);

(3)          The annual revenue saving of £17,800 be transferred into an earmarked reserve for future IT renewals and replacements as detailed in Table 3 contained in Annexe 1 to the report (considered exempt from publication).

Report author: Mark Lumley

Publication date: 28/09/2016

Date of decision: 27/09/2016

Decided at meeting: 27/09/2016 - Strategy and Resources Committee