To agree the operation of the ICT datacentre
and infrastructure.
The Committee agreed:
(1) Option 3C for the Joint Data Centre with Elmbridge Borough Council hosted at a third party datacentre;
(2) The funding from existing capital budgets of £63,000 and the use of £139,600 additional capital funds as detailed in Table 3 contained in Annexe 1 to the report (considered exempt from publication);
(3) The annual revenue saving of £17,800 be transferred into an earmarked reserve for future IT renewals and replacements as detailed in Table 3 contained in Annexe 1 to the report (considered exempt from publication).
Report author: Mark Lumley
Publication date: 28/09/2016
Date of decision: 27/09/2016
Decided at meeting: 27/09/2016 - Strategy and Resources Committee