Decision Maker: Strategy and Resources Committee
Decision status: For Determination
Is Key decision?: No
Is subject to call in?: No
The Committee agreed:
(1) Not to make an additional contribution from the Community Infrastructure Levy (CIL) towards the cost of the Plan E Epsom Town Centre Highway and Public Realm Improvement Scheme;
(2) That blockwork equivalent to the existing materials in the public realm, the cost of which could be afforded across the entire scheme within the established budget, be the material used for surfacing paths in various phased of the scheme and for surfacing the market place and other locations.
Report author: Mark Berry
Publication date: 28/06/2017
Date of decision: 27/06/2017
Decided at meeting: 27/06/2017 - Strategy and Resources Committee