Decision Maker: Strategy and Resources Committee
Decision status: For Determination
Is Key decision?: No
Is subject to call in?: No
Following consideration, it was resolved that the Committee:
(1) Agreed to note the progress and anticipated spend at the end of the current year 2020/21;
(2) Agreed to transfer the £68,000 projected underspend on 2020/21’s programme back to the Planned Maintenance Reserve for use in 2021/22;
(3) Agreed to approve the 2021/22 planned maintenance programme at an estimated cost of £315,000 as set out in Appendix 2;
(4) Agreed to delegate authority to the Head of Property and Regeneration to make changes within the 2021/22 planned maintenance programme to cover unforeseen matters (such as tender price variances) of up to, but not exceeding £20,000; subject to the Council’s financial and contract requirements.
Report author: Mark Shephard
Publication date: 29/01/2021
Date of decision: 28/01/2021
Decided at meeting: 28/01/2021 - Strategy and Resources Committee