Decision Maker: Strategy and Resources Committee
Decision status: For Determination
Is Key decision?: No
Is subject to call in?: No
Following consideration, the Committee unanimously resolved to:
(1) Agree for Bourne Hall Lodge to be refurbished for residential accommodation, as detailed in Option 1 (Appendix 2, paragraphs 1.1 – 1.12 of the report).
(2) Agree to fund the refurbishment budget of up to £340,000 from S106 developer funds.
(3) Nominate and authorise the Head of Property & Regeneration, Head of Housing & Community in consultation with the Director of Corporate Services and Head of Legal, to take all necessary actions further to the above decision being made that commit resources, as is necessary and appropriate, to progress the selected option to completion.
Report author: Mark Shephard
Publication date: 16/07/2025
Date of decision: 15/07/2025
Decided at meeting: 15/07/2025 - Strategy and Resources Committee
Accompanying Documents: