Decision Maker: Environment Committee
Decision status: For Determination
Is Key decision?: No
Is subject to call in?: No
Report concerning the future of the River
Hogsmill Stepping Stones
Following consideration the Committee resolved to:
(1) Agree to Option 3: Do not agree to take on the liability for the steps and stepping stones and acknowledge the EA will remove them and agree to deliver a new footbridge as an alternative safer fully accessible crossing point subject to being granted CIL funding and securing additional funding for the design and planning of a footbridge.
(2) Note the submission of the CIL application for funding the construction of a new pedestrian footbridge.
Report author: Stewart Cocker
Publication date: 01/07/2026
Date of decision: 30/06/2026
Decided at meeting: 30/06/2026 - Environment Committee
Accompanying Documents: