12 Final Capital Proposals - 2025/26 PDF 252 KB
This report sets out the final proposals for the 2025/26 Capital Programme and seeks guidance as to which of these should be taken to the relevant policy committee in January 2025 to seek support for inclusion within the 2025/26 Capital Programme.
Additional documents:
Minutes:
Members provided the following feedback on each proposal:
a) Environment 1 – Stew Ponds Removal of Silt
Members discussed the urgency of the works and how this scheme had been proposed for several years but deferred. It was agreed to progress this scheme committee under the 2025/26 capital programme.
b) Environment 2 – Uppermill Pond Bank Replacement
These works were considered essential and therefore it was agreed to progress this scheme under the 2025/26 capital programme.
c) Environment 3 – Ashley Centre Car Park Overcoating Waterproof Membrane
The rationale for doing the works in phases was discussed and it was agreed to progress level 1 only for the 2025/26 capital programme.
d) Environment 4 – Court Recreation Ground Renewal of 3G Football Pitch
It was agreed that this scheme should progress and 3G was confirmed as the best option. Members requested that Environment committee revisit the fees to ensure they are in line with other local pitches and additional income to repay investment.
e) Environment 5 – Playground Renovation and Surface Renewal
Members agreed that only the most in need playground should progress and recommended Hardwick’s Yard be funded from the budgeted revenue contribution to capital for 2025/26.
f) Community & Wellbeing 1 – Playhouse Stage Lighting and Dimmers
These works were considered essential to the continued operation of the theatre and therefore it was agreed to progress this scheme under the 2025/26 capital programme.
g) Community & Wellbeing 3 – Bourne Hall Replacement of Windows – Phase 2
These works were considered essential to the continued operation of Bourne Hall. To realise economies of scale from combining this scheme with the phase 1 works taking place in 2024/25 Members recommended a report be taken to Full Council in December 2024 to seek approval for the budget in time to coordinate with the tenders which have been received.
Following consideration of the above matters and the report’s contents, the Group moved to consider the report recommendations, which were agreed as follows:
(1) Provide guidance on which of the final proposals should be taken to the relevant policy committee in January 2025 to seek support for inclusion within the 2025/26 Capital Programme.
(2) Identify which schemes should be approved and which should be removed from the list of proposals in section 4.1 of the report.