26 Nonsuch Planned Maintenance Update and New Priority Works for 2026-27
PDF 322 KB
|
This report provides:
|
Additional documents:
Minutes:
The Committee received a report providing an update on the current financial year 2025-26 priority planned maintenance programme (including any additional Health & Safety and emergency works undertaken during the year) and seeking approval for the forthcoming 2026-27 priority planned maintenance works.
The Committee considered the following matters:
a) Mansion Boiler. In response to a question from a Member, the Senior Surveyor explained that the Mansion had recently had new a boiler installed, with an anticipated lifespan of c.20yrs. He informed the Committee that heat pumps would not be compatible at the Mansion.
b) Car Park Resurfacing. In response to a question from a Member in respect of potholes in the car parks, the Senior Surveyor stated that it would cost c.£130k to carry out a full resurfacing operation, which was not available within the Committee’s funds.
Following consideration, the Committee unanimously resolved to:
(1) Note the progress of the works (including the additional Health & Safety and emergency works) carried out during the current financial year 2025-26.
(2) Approve the proposed planned maintenance priority works for 2026-27.