Planned Maintenance 6 month update

Meeting: 28/11/2017 - Strategy and Resources Committee (Item 31)

31 Planned Maintenance 6 month update pdf icon PDF 100 KB

The report reviews progress and changes to the planned maintenance programme at mid-year and advises of changes made under delegated authority.

Additional documents:

Decision:

The Committee:

(1)          Received the current position and progress on the planned maintenance programme;

(2)          Noted changes made to the programme under delegated authority.

Minutes:

Note: Councillor Eber Kington resumed Chairmanship for the remainder of the meeting.

The Committee received a report reviewing progress and changes to the planned maintenance programme at mid-year. The report also advised members of changes made to the agreed programme in accordance with authority delegated to Officers.

Progress on the current programme was noted as follows:

 

Scheme

2017/18

The Works

Forecast

Spend

£

Progress

Bourne Hall

Provide air conditioning to office

3,901

Complete

Ewell High Street car park

Resurfacing

38,119

Complete

Ashley Centre Car Park

Health & Safety works

----

These works now included in Capital bid for next year

Cemetery chapel

External decoration to entrance

4,689

Complete

Cox lane

External decoration & window Replacement

27,000

Due to complete end of November

Longmead Depot

Refurbishment of WC’s

21,090

Complete

Various

Hard surface repairs

20,000

Ongoing at various sites

Alex Rec Main pavilion

Damp Proofing works

41,565

Complete

Auriol Pavilion

New boiler & associated works

35,000

Currently out to tender

Harriers Centre

Redecorations internal & External

20,535

Complete

Asbestos

Re-inspections

7,730

Surveys complete

Fire Risk Assessments

Remedial works

12,186

Ongoing

Electrical works

Testing and remedial electrical works

45,000

Ongoing

Energy Efficiency

Various improvements and repairs to meters

11,083

Ongoing

Water Efficiency

Repairs to leaks & water efficiencies

10,000

Ongoing

Watercourses

Clearance of large amounts of rubbish dumped in watercourses

4,675

Ongoing

Total

 

302,573

 

The Committee noted that he following changes had been made to the approved programme in accordance with authority delegated to Officers:

a)            Additional spend on Bourne Hall Lodge to carry out repairs and redecorations as a result of water damage to the kitchen (£2,350);

b)            Additional spend on re-surfacing Ewell High Street Car Park following tender process (£2,546);

c)            Additional spend on Longmead Depot toilet refurbishment as a result in a change to the scope of works and resultant tender process (£6,000)

d)            Energy efficiency works necessitated by failure of old energy meters (£6,083)

These works did not result in an additional cost to the programme.  It was noted that the Ashley Centre Car Park health and safety repairs (£20K) was now a capital bid.

The budget at this stage appeared to cover the completed and intended works for 2017/18.  The property reserve held at 1 April 2017 was £402k.  This balance was forecast to reduce to £297k as at 31 March 2018 following the use of reserves in 2017/18. The report highlighted that beyond 2017/18, the existing budget of £210k would be insufficient to continue to maintain Council buildings and assets. A budget increase would be considered in the revised Asset Management Plan to be proposed by the Head of Property at a later date.

Accordingly, the Committee:

(1)          Received the current position and progress on the planned maintenance programme;

(2)          Noted changes made to the programme under delegated authority.