17 Planned Maintenance Update September 2017 PDF 81 KB
This report provides an update on the priority works and outlines the works proposed to be undertaken in 2017/2018.
Additional documents:
Minutes:
Tony Foxwell, Property Projects Manager, updated the Committee on the progress of outstanding planned maintenance items as follows:
Pathway between Nonsuch Mansion and Sparrow Farm Lodge |
First phase of repairs have been completed – Cost £16,000 out of an allocation of £20,000 |
Separation of Services for Friends of Nonsuch |
Completed |
Nonsuch Mansion/Tractor shed Electrical Remedial works |
Works programmed to start at the end of October for four weeks |
Nonsuch Mansion House Fire Protection works |
Work to be tendered imminently |
General window repairs |
A schedule of works will be produced in November |
Flooding to access road and outside childrens nursery |
Projects Manager will be meeting with contractors to obtain quotes to repair the soakaways causing the flooding |
Since the publication of the agenda a further priority item had been identified which required urgent attention, i.e.: repair to the access road. The Committee noted that the Projects Manager was in the process of obtaining quotes and the cost of the repairs would be funded the 2017/2018 maintenance budget.
A further project had been identified, public toilet refurbishment, which would likely be funded from the 2018/2019 maintenance budget. The estimated cost of £40,000 had been based on the cost of similar completed projects.
Having considered the planned maintenance report, the Committee:
(1) Noted the contents of the report and update on progress of Planned Priority Maintenance work.
(2) Noted the additional priority works identified for 2018/2019.