Planned Maintenance Update September 2017

Meeting: 30/10/2017 - Nonsuch Park Joint Management Committee (Item 17)

17 Planned Maintenance Update September 2017 pdf icon PDF 81 KB

This report provides an update on the priority works and outlines the works proposed to be undertaken in 2017/2018.

Additional documents:

Minutes:

Tony Foxwell, Property Projects Manager, updated the Committee on the progress of outstanding planned maintenance items as follows:

 

Pathway between Nonsuch Mansion and Sparrow Farm Lodge

First phase of repairs have been completed – Cost £16,000 out of an allocation of £20,000

Separation of Services for Friends of Nonsuch

Completed

Nonsuch Mansion/Tractor shed Electrical Remedial works

Works programmed to start at the end of October for four weeks

Nonsuch Mansion House Fire Protection works

Work to be tendered imminently

General window repairs

A schedule of works will be produced in November

Flooding to access road and outside childrens nursery

Projects Manager will be meeting with contractors to obtain quotes to repair the soakaways causing the flooding

Since the publication of the agenda a further priority item had been identified which required urgent attention,  i.e.: repair to the access road.  The Committee noted that the Projects Manager was in the process of obtaining quotes and the cost of the repairs would be funded the 2017/2018 maintenance budget.

A further project had been identified, public toilet refurbishment, which would likely be funded from the 2018/2019 maintenance budget.  The estimated cost of £40,000 had been based on the cost of similar completed projects.

Having considered the planned maintenance report, the Committee:

(1)            Noted the contents of the report and update on progress of Planned Priority Maintenance work.

(2)            Noted the additional priority works identified for 2018/2019.