62 Planned Maintenance Programme 2019-20 PDF 106 KB
The Committee is asked to consider and agree the planned maintenance programme for 2019/20.
Additional documents:
Decision:
Following consideration, it was resolved:
That the Committee:
(1) Approved the 2019/20 planned maintenance programme at an estimated cost of £280,000.
(2) Approved the carry forward of the underspend on 2018/19’s programme, for use as funding towards the proposed 2019/20 programme and outstanding Legionella remedial works.
(3) Authorised officers to make changes within the programme up to but not exceeding £10,000.
Minutes:
The Committee received a report presenting the 2019-20 planned maintenance programme. The report also provided a progress update on the 2018/19 planned maintenance programme and requested approval to carry forward, to 2019/20, specific works and unspent budget from 2018/19. The following corrections to typographical errors within the report were noted:
· That the wording “Annex 2” in paragraph 2.2 be replaced with “Annex 1”.
· That the wording “Annex 3” in paragraphs 3.1 and 3.3 be replaced with “Annex 2”.
Following consideration, it was resolved:
That the Committee:
(1) Approved the 2019/20 planned maintenance programme at an estimated cost of £280,000.
(2) Approved the carry forward of the underspend on 2018/19’s programme, for use as funding towards the proposed 2019/20 programme and outstanding Legionella remedial works.
(3) Authorised officers to make changes within the programme up to but not exceeding £10,000.