Meeting: 11/04/2019 - Planning Committee (Item 70)

70 Sunnybank House 39A East Street Epsom KT17 1BL 18/01508/REM pdf icon PDF 126 KB

Variation of Condition 8 (Contaminated land) of planning permission 17/01755/FUL to permit the verification report to be completed pre-occupation rather than pre-commencement.

Additional documents:

Minutes:

Description

Variation of Condition 8 (Contaminated Land) of planning permission 17/01755/FUL to permit verification report to be completed pre-occupation rather than pre-commencement.

Decision

Variation of Condition is PERMITTED, subject to the following:

Part A

Subject to a new legal agreement (under the same terms as the extant agreement) being completed by 12th July 2019 and signed to secure the following heads of terms:

         A Travel Plan Monitoring Fee

The Committee authorise the Head of Planning to grant planning permission subject to the conditions detailed below.

Part B

In the event that the section 106 Agreement referred to in Part A is not completed by 12th July 2019, the Head of Planning be authorised to refuse the application for the following reason:

·                 In the absence of a completed legal obligation under section 106 of the Town and Country Planning Act 1990 (as amended) the applicant has failed to comply with Policy CS5 of the Core strategy 2007

Conditions:

(1)            The development hereby permitted shall be commenced within 3 years from the 18 September 2018, the date of the originally approved application 17/01755/FUL that is subject to this application to variation.

Reason: In order to comply with Section 91 of the Town and Country Planning Act, 1990. (As amended)

(2)            Prior to the commencement of development, details and samples of the external materials to be used for the development shall be submitted to and approved in writing by the local planning authority. The development shall be carried out in accordance with the approved details.

Reason: To secure a satisfactory appearance in the interests of the visual amenities and character of the locality in accordance with Policy CS5 of the Core Strategy (2007) and Policies DM9 and DM10 of the Development Management Policies 2015.

(3)            No development shall take place until full details, of both hard and soft landscape proposals, including a schedule of landscape maintenance for a minimum period of 5 years and the planting of three trees in front of the building, have been submitted to and approved in writing by the local planning authority. The approved landscape scheme (with the exception of planting, seeding and turfing) shall be implemented prior to the occupation of the development hereby approved and thereafter retained.

Reason: To ensure the provision, establishment and maintenance of an appropriate landscape scheme in the interests of the visual amenities of the locality in accordance with Policy CS5 of the Core Strategy (2007) and Policies DM5 and DM9 of the Development Management Policies 2015.

(4)            A report is to be submitted to the Local Planning Authority, within 6 months of the commencement of any use of any part of the building, to demonstrate that the renewable technologies (as detailed in the submitted Sustainability Statement)  hereby approved have been fully implemented and are functioning.

Reason: In order to promote sustainable construction in accordance with Policy CS6 of the Core Strategy 2007.

(5)            The student accommodation hereby approved shall not be occupied until they have achieved a water  ...  view the full minutes text for item 70