This report summarises the proposed 2020/21 capital programme for Strategy & Resources Committee. Approval is sought for the programme to be submitted to Council in February 2020.

Additional documents:

Decision:

Following consideration, it was resolved:

That the Committee:

(1)      Submited the Capital Programme for 2020/21 as identified in section 4 of this report to the Council for approval.

 

Minutes:

The Committee received a report summarising the proposed 2020/21 capital programme for Strategy & Resources Committee. Approval was sought for the programme to be submitted to Council in February 2020.

Two schemes were recommended to the Committee for submission to the Council:

·                     ICT Programme of Works

·                     Clocktower envelope repairs

Following consideration, it was resolved:

That the Committee:

(1)      Submitted the Capital Programme for 2020/21 as identified in section 4 of the report to the Council for approval.