Agenda item

57 Salisbury Road Worcester Park Surrey KT4 7DE

Redevelopment of the site for 17 apartments with carport, car parking, cycle store, bin store and associated external works.


Minutes:

Description

Redevelopment of the site for 17 apartments with carport, car parking, cycle store, bin store and associated external works.

Decision

The Committee received a presentation from the Planning Officer.

The following points were raised by the Committee:

a)            Housing mix: Members raised concerns regarding the proposed housing mix. It was noted that the previous approved Application relating to this site allowed the removal of the 3-bedroom property as the housing mix and internal layout was more suited to 2-bedroom properties. It was noted that although the housing mix is not policy-compliant, the additional 2 units make it appropriate.

b)           Amenity space: It was noted that a number of the apartments would have private amenity space by means of a private balcony, and others would have access to communal amenity space.

c)            Optimisation: Members raised concerns regarding the optimisation of the site. It was noted that Officers deemed it an optimal use of the site, with no impact on neighbouring amenity and 2 additional housing units.

Following consideration, the Committee resolved with 7 Members voting for and 6 Members voting against that:

The Application be APPROVED subject to the following:

Part A

22.1 Subject to a legal agreement being completed and signed by the 16th April 2021 to secure the following heads of terms:

Viability Review

Implementation of a review mechanism for the submission of a revised viability statement

S106 monitoring fee, to monitor and sign off compliance of the s106 obligation The Committee authorise the Head of Planning to grant planning permission subject to the conditions detailed below.

Part B

22.2 In the event that the section 106 Agreement referred to in Part A is not completed by 16th April 2021, the Head of Planning be authorised to refuse the application for the following reason:

In the absence of a completed legal obligation under section 106 of the Town and Country Planning Act 1990 (as amended), the applicant has failed to comply with Policy CS9 (Affordable Housing and meeting Housing Needs) in relation to the provision of 6 on site affordable housing units.

Condition(s):

(1)          The development hereby permitted shall be begun before the expiration of three years from the date of this permission.

Reason: To comply with Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 (1) of the Planning and Compulsory Purchase Act 2005.

(2)          The development hereby permitted shall be carried out in accordance with the following approved plans and documents:

2019 - P0043 - LP (Site Location Plan) (1:1250)

2019 - P0043 – 200 (Coloured Site Layout) (1:250)

2019 - P0043 - 201 (Proposed Site Information Plan) (1:250)

2019 - P0043 - 202 (Proposed Floor Plans) (1:100)

2019 - P0043 - 203 (Proposed Elevations) (1:100)

2019 - P0043 - 204 (Proposed Street Scene) (1:250)

2019 - P0043 - 205 (Proposed Bin Store) (1:100)

2019 - P0043 - 206 (Proposed Cycle Store) (1:100)

Reason: For the avoidance of doubt and in the interests of proper planning as required by Policy CS5 of the Core Strategy (2007).

(3)          Prior to the commencement of development, details and samples of the external materials to be used for the development shall be submitted to and approved in writing by the local planning authority. The development shall be carried out in accordance with the approved details.

Reason: To secure a satisfactory appearance in the interests of the visual amenities and character of the locality in accordance with Policy CS5 of the Core Strategy (2007) and Policies DM9 and DM10 of the Development Management Policies 2015.

(4)          No development shall take place until full details, of both hard and soft landscape proposals, including a schedule of landscape maintenance for a minimum period of 5 years, have been submitted to and approved in writing by the local planning authority. The landscaping shall incorporate the planting of native species of trees and shrubs. The approved landscape scheme (with the exception of planting, seeding and turfing) shall be implemented prior to the occupation of the development hereby approved and thereafter retained.

Reason: To ensure the provision, establishment and maintenance of an appropriate landscape scheme in the interests of the visual amenities of the locality in accordance with Policy CS5 of the Core Strategy (2007) and Policies DM5 and DM9 of the Development Management Policies 2015.

(5)          No development shall take place until details of existing and proposed finished site levels, finished floor and ridge levels of the buildings to be erected, and finished external surface levels have been submitted to and approved in writing by the local planning authority. The development shall thereafter be constructed in accordance with the approved details.

Reason: In order to safeguard the visual amenities of the area and the amenities of the occupiers of neighbouring properties in accordance with Policy CS5 of the Core Strategy (2007) and PolicyDM10 of the Development Management Policies 2015.

(6)          The first and second floor rear bedroom windows to Flat 7 and 13, of the development hereby permitted shall be glazed with obscure glass of no less than obscurity level 3 and permanently fixed shut unless the parts of the windows which can be opened are more than 1.7 metres above the floor of the room in which the window is installed, and shall thereafter be permanently retained as such.

Reason: To safeguard the privacy of the occupants of adjoining properties in accordance with Policy DM10 of the Development Management Policies 2015.

(7)          No demolition, site clearance or building operations shall commence until an updated site specific Arboricultural Method Statement has been submitted to, and approved in writing by the local planning authority, and until the protective fencing and other protection measures as shown in the approved Arboricultural Method Statement have been installed. At all times until the completion of sthe development, such fencing and protection measures shall be retained as approved. Within all fenced areas, soil levels shall remain unaltered and the land kept free of vehicles, plant, materials and debris.

Reason: To protect the trees on site which are to be retained in the interests of the visual amenities of the locality in accordance with Policy CS5 of the Core Strategy (2007) and Policies DM5 and DM9 of the Development Management Policies 2015.

(8)          No development shall take place until details of all boundary treatment have been submitted to and approved in writing by the local planning authority. The approved scheme shall be implemented prior to the first occupation of the development or phased as agreed in writing by the local planning authority. The approved scheme shall thereafter be retained.

Reason: To secure a satisfactory appearance in the interests of the visual amenities and character of the locality in accordance with Policy CS5 of the Core Strategy (2007) and Policies DM9 and DM10 of the Development Management Policies 2015.

(9)          The demolition works hereby permitted shall not be carried out before a contract for the carrying out of the works of redevelopment has been made and evidence of the construction contract has been submitted to and approved in writing by the local planning authority.

Reason: To ensure that premature demolition does not take place before development works start in order to safeguard the visual amenities of the area Policy CS5 of the Core Strategy (2007) and Policies DM8, DM9 and DM10 of the Development Management Policies 2015.

(10)       The development hereby permitted shall not commence until details of hard surfaced areas have been submitted to and approved in writing by the local planning authority. Such details shall show that the hard surface will be porous or permeable, or shall direct surface water to a porous or permeable surface within the site. The development shall be carried out fully in accordance with the approved details and so maintained.

Reason: To reduce surface water run-off from the site in line with Policy CS6 of the Core Strategy (July 2007) and Policy DM10 of the Development Management Policies 2015.

(11)       Notwithstanding the submitted plans, no part of the development shall be first occupied unless and until a vehicular bell-mouth access, with tactile paving and dropped kerbs at the pedestrian crossing point, has been constructed in accordance with a revised scheme to be submitted to and approved in writing by the Local Planning Authority and thereafter all shall be permanently retained.

Reason: The above condition is required in order that the development should not prejudice highway safety, nor cause inconvenience to other highway users, and to accord with the National Planning Policy Framework 2018 and DM 35 Transport and New Development of the Epsom and Ewell Borough Council Development Management Policies Document September 2015.

(12)       The means of access to the development shall be from Salisbury Road only. The development hereby approved shall not be first occupied unless and until the existing access from the site to Cromwell Road has been permanently closed and any kerbs, verge, footway, fully reinstated.

Reason: In order that the development should not prejudice highway safety nor cause inconvenience to other highway users and to accord with the provisions of policy CS16 of the Core Strategy 2007.

(13)       Notwithstanding the proposed Construction Transport Management Plan, no development shall commence until a Construction Transport Management Plan, to include details of:

d)           parking for vehicles of site personnel, operatives and visitors

e)            loading and unloading of plant and materials

f)             storage of plant and materials

g)           programme of works (including measures for traffic management)

h)           provision of boundary hoarding behind any visibility zones

i)             measures to prevent the deposit of materials on the highway

has been submitted to and approved in writing by the Local Planning Authority. Only the approved details shall be implemented during the construction of the development.

(14)       No new development shall be occupied until space has been laid out within the site in accordance with the approved plans for a maximum of 17 cars and a minimum of 17 cycles to be parked, and for vehicles to turn so that they may enter and leave the site in forward gear. The parking/turning area shall be used and retained exclusively for its designated purpose.

Reason: In order that the development should not prejudice highway safety nor cause inconvenience to other highway users and to accord with the provisions of policy CS16 of the Core Strategy 2007.

(15)       No part of the development shall be first occupied unless and until the proposed vehicular access to Salisbury Road has been constructed and provided with visibility zones in general accordance with the approved plans and thereafter the visibility zones shall be kept permanently clear of any obstruction over 0.6m high.

Reason: In order that the development should not prejudice highway safety nor cause inconvenience to other highway users and to accord with the provisions of policy CS16 of the Core Strategy 2007.

(16)       Prior to the commencement of the development, details of sustainability measures shall be submitted to and approved in writing by the local planning authority. These details shall demonstrate how the development would be efficient in the use of energy, water and materials including means of providing the energy requirements of the development from renewable technologies. The development shall be carried out in strict accordance with the approved details prior to the first occupation of the building, shall be maintained as such thereafter and no change shall take place without the prior written consent of the local planning authority.

Reason: To ensure that measures to make the development sustainable and efficient in the use of energy, water and materials are included in the development in accordance with Policy CS6 of the Core Strategy (2007).

(17)       The development shall not be occupied until the bat and bird boxes and wildlife log pile have been installed in accordance with the Biodiversity Enhancement Measures contained in the Bat Survey and Biodiversity Report - September 2020.

Reason: To enhance biodiversity and nature habitats in accordance with Policy CS3 of the Core Strategy (2007) and Policy DM4 of the Development Management Policies 2015.

(18)       The development hereby permitted shall not commence until details of the design of a surface water drainage scheme have been submitted to and approved in writing by the planning authority. The design must satisfy the SuDS Hierarchy and be compliant with the national Non-Statutory Technical Standards for SuDS, NPPF and Ministerial Statement on SuDS. The required drainage details shall include:

a)            The results of infiltration testing completed in accordance with BRE Digest: 365 and confirmation of groundwater levels.

b)           Evidence that the proposed final solution will effectively manage the 1 in 30 & 1 in 100 (+40% allowance for climate change) storm events and 10% allowance for urban creep, during all stages of the development. The final solution should follow the principles set out in the approved drainage strategy. If infiltration is deemed unfeasible, associated discharge rates and storage volumes shall be provided using a maximum discharge rate of 1.0 l/s.

c)            Detailed drainage design drawings and calculations to include: a finalised drainage layout detailing the location of drainage elements, pipe diameters, levels, and long and cross sections of each element including details of any flow restrictions and maintenance/risk reducing features (silt traps, inspection chambers etc.).

d)           A plan showing exceedance flows (i.e. during rainfall greater than design events or during blockage) and how property on and off site will be protected.

e)            Details of drainage management responsibilities and maintenance regimes for the drainage system.

f)             Details of how the drainage system will be protected during construction and how runoff (including any pollutants) from the development site will be managed before the drainage system is operational.

Reason: To ensure the design meets the national Non-Statutory Technical Standards for SuDS and the final drainage design does not increase flood risk on or off site, in accordance with Policy CS6 of the Epsom and Ewell Core Strategy (2007) and Policy DM19 of the Development Management Policies 2015.

(19)       Prior to the first occupation of the development, a verification report carried out by a qualified drainage engineer must be submitted toand approved by the Local Planning Authority. This must demonstrate that the drainage system has been constructed as per the agreed scheme (or detail any minor variations), provide the details of any management company and state the national grid reference of any key drainage elements (surface water attenuation devices/areas, flow restriction devices and outfalls).

Reason: To ensure the Drainage System is constructed to the National Non-Statutory Technical Standards for SuDS, in accordance with Policy CS6 of the Epsom and Ewell Core Strategy (2007) and Policy DM19 of the Development Management Policies 2015.

(20)       Ground contamination and ground gas assessment

Following any necessary demolition and prior to the commencement of any further development, the following shall be undertaken in accordance with current best practice guidance: a desk study, site investigation and risk assessment to determine the existence, extent and concentrations of any made ground/fill, ground gas (including hydrocarbons) and contaminants (including asbestos) with the potential to impact sensitive receptors on and offsite.

The results of the investigation and risk assessment shall be submitted to and approved by the Local Planning Authority; and if ground/groundwater contamination, filled ground and/or ground gas is found to present unacceptable risks, a detailed scheme of risk management measures shall be designed and submitted to the Local Planning Authority for approval.

Reason: To ensure that risks from land contamination to the future users of the land and neighbouring land are minimised, together with those to controlled waters, property and ecological systems, and to ensure that the development can be carried out safely without unacceptable risks to workers, neighbours and other offsite receptors, in accordance with Policy DM17 of the Development Management Policies 2015 and the National Planning Policy Framework.

(21)       Remediation

Prior to any occupation of the site, the approved remediation scheme prepared under Condition 19 must be carried out in accordance with its terms. Following completion, a verification report that demonstrates the effectiveness of the remediation carried out must be produced, and is subject to the approval in writing of the Local Planning Authority.

Reason: To ensure that risks from land contamination to the future users of the land and neighbouring land are minimised, together with those to controlled waters, property and ecological systems, and to ensure that the development can be carried out safely without unacceptable risks to workers, neighbours and other offsite receptors, in accordance with Policy DM17 of the Development Management Policies 2015 and the National Planning Policy Framework.

(22)       Unexpected contamination

In the event that contamination is found at any time when carrying out the approved development that was not previously identified it must be reported in writing immediately to the Local Planning

Authority. In that event, an investigation and risk assessment must be undertaken and where remediation is deemed necessary a remediation scheme must be prepared which is subject to the approval in writing of the Local Planning Authority. Following completion of measures identified in the approved remediation scheme a verification report must be prepared, which is subject to the approval in writing of the Local Planning Authority.

Reason: To ensure that risks from land contamination to the future users of the land and neighbouring land are minimised, together with those to controlled waters, property and ecological systems, and to ensure that the development can be carried out safely without unacceptable risks to workers, neighbours and other offsite receptors, in accordance with Policy DM17 of the Development Management Policies 2015 and the National Planning Policy Framework.

(23)       The development hereby approved shall not be first occupied unless and until four parking spaces are provided with a fast charge socket(current minimum requirement: 7kw Mode 3 with Type 2 connector -230 v AC 32 amp single phase dedicated supply) in accordance with a scheme to be submitted to and approved in writing by the Local Planning Authority.

Reason: The condition above is required in order that the development should not prejudice highway safety, nor cause inconvenience to other highway users, and to accord with the National Planning Policy Framework 2018 and Policy DM 36 Sustainable Transport for New Development, of the Epsom & Ewell Borough Council Development Management Policies Document September2015.

(24)       The development shall not be occupied until a Car Parking Management Plan setting out provisions for the management and use of the proposed parking has been submitted to and agreed in writing by the Local Planning Authority. These details shall be submitted for approval by the Local Planning Authority and only the approved details shall be implemented and retained as approved unless otherwise agreed.

Reason: To ensure the efficient and functional use of the car parking area, to safeguard the amenity of future occupiers of the approved development and to ensure that the development does not prejudice highway safety nor cause inconvenience to other highway users in compliance with Policy DM10, DM37 of the Development Management Policies Document 2015 and Policy CS16 of the Core Strategy 2007.

Informative(s):

(1)          The Council confirms that in assessing this planning application it has worked with the applicant in a positive and proactive way, in line with the requirements of paragraph 38 of the National Planning Policy Framework 2018.

(2)          This form of development is considered liable for the Community Infrastructure Levy (CIL). CIL is a non-negotiable charge on new developments which involve the creation of 100 square metres or more of gross internal floorspace or involve the creation of a new dwelling, even when this is below 100 square metres. The levy is a standardised, non-negotiable charge expressed as pounds per square metre, and are charged on the net additional floorspace generated by a development. You will receive more information regarding the CIL in due course.

More information and the charging schedule are available online: http://www.epsom-ewell.gov.uk/NR/exeres/74864EB7-F2ED-4928-AF5A-72188CBA0E14,frameless.htm?NRMODE=Published

(3)          No construction work shall be carried out in such a manner as to be audible at the site boundary before 07:30 hours or after 18:30 hours Monday to Friday; no construction work shall be audible at the site boundary before 8:00 or after 13:00 hours on Saturdays and no construction work of any nature shall be carried out on Sundays or Bank/Public Holidays.

(4)          The permission hereby granted shall not be construed as authority to carry out any works on the highway or any works that may affect a drainage channel/culvert or water course. The applicant is advised that a permit and, potentially, a Section 278 agreement must be obtained from the Highway Authority before any works are carried out on any footway, footpath, carriageway, verge or other land forming part of the highway. All works on the highway will require a permit and an application will need to be submitted to the County Council's Street Works Team up to 3 months in advance of the intended start date, depending on the scale of the works proposed and the classification of the road. Please see: http://www.surreycc.gov.uk/roads-and-transport/road-permits-andlicences/the-traffic-management-permit-scheme

 

(5)          The applicant is also advised that Consent may be required under Section 23 of the Land Drainage Act 1991. Please see: www.surreycc.gov.uk/people-and-community/emergency-planningandcommunity-safety/flooding advice

 

Supporting documents: