Town Hall Site

17/07/2023 - Town Hall Site

Following consideration, the Committee unanimously resolved to:

(1)      Agree the procurement of specialist regeneration and development consultancy support as detailed in the report.

(2)      Agree a budget of up to £150,000 to be funded from the Corporate Projects Reserve.

(3)      Delegate to the Acting Director of Environment, Housing & Regeneration and the Head of Property & Regeneration in consultation with the Chief Finance Officer, to commission the work.

(4)      Note a report would be brought back to Committee at the earliest opportunity following completion of the work.